Assessment Year | 1984 |
---|---|
Principal Product | FACE BRICK |
NAICS |
n/a
|
SIC | 3251: Brick and Structural Clay Tile |
Sales Range | $5 M to 10M |
# of Employees | 100 |
Plant Area |
n/a
|
Annual Production | 75,000,000
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $322,322 | 7,388,628 |
kWh
|
$0.044 |
Natural Gas | $15,827 | 2,936 |
MMBtu
|
$5.39 |
Coal | $358,884 | 199,521 |
MMBtu
|
$1.80 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,526 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,915 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Coal Savings |
---|---|---|---|---|---|---|
01 | 2.2515: Use optimum thickness insulation | $3,915 | $11,018 | - |
$3,915
-
MMBtu
|
|
02 | 2.5123: Reduce fluid flow rates | $9,120 | $4,000 |
$9,120
207,796
kWh
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $491 | - |
$491
11,137
kWh
|
- | |
TOTAL RECOMMENDED | $13,526 | $15,018 |
$9,611
218,933
kWh
|
$3,915
-
MMBtu
|
||
TOTAL IMPLEMENTED | $3,915 | $11,018 | - |
$3,915
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs