Assessment Year | 1984 |
---|---|
Principal Product | WOOD LAMINANTS |
NAICS |
n/a
|
SIC | 2491: Wood Preserving |
Sales Range | $5 M to 10M |
# of Employees | 85 |
Plant Area |
n/a
|
Annual Production | 6,000
ton
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $117,198 | 2,082,943 |
kWh
|
$0.056 |
Natural Gas | $102,572 | 21,539 |
MMBtu
|
$4.76 |
Fuel Oil #2 | $7,750 | 1,085 |
MMBtu
|
$7.14 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $27,076 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,058 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.6212: Turn off equipment during breaks, reduce operating time | $7,818 | $3,675 |
$4,914
87,339
kWh
|
$2,904
-
MMBtu
|
- | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $12,425 | - |
$12,425
218,054
kWh
|
- | - | |
03 | 2.2511: Insulate bare equipment | $3,155 | $5,000 | - |
$3,155
-
MMBtu
|
- | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $755 | - | - |
$1,055
-
MMBtu
|
$(-300.0) | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,656 | $25 |
$2,656
46,600
kWh
|
- | - | |
06 | 2.6212: Turn off equipment during breaks, reduce operating time | $200 | - |
$200
3,517
kWh
|
- | - | |
07 | 2.6212: Turn off equipment during breaks, reduce operating time | $67 | - |
$67
1,172
kWh
|
- | - | |
TOTAL RECOMMENDED | $27,076 | $8,700 |
$20,262
356,682
kWh
|
$7,114
-
MMBtu
|
$(-300.0) | ||
TOTAL IMPLEMENTED | $19,058 | $5,025 |
$15,148
265,826
kWh
|
$4,210
-
MMBtu
|
$(-300.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs