ITAC Assessment: TN0223
ITAC logo
ITAC Assessment: TN0223
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1984
Principal Product POLYURETHANE
NAICS
n/a
SIC 2822: Synthetic Rubber (Vulcanizable Elastomers)
Sales Range $50
M
to 100
M
# of Employees 300
Plant Area
n/a
Annual Production 25,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $197,092 4,368,699
kWh
Natural Gas $96,584 20,226
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $40,864 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $31,969

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $18,629 $12,000 - $18,629
-
MMBtu
02 2.7221: Lower temperature during the winter season and vice-versa $11,022 $792 - $11,022
-
MMBtu
03 2.6124: Establish equipment maintenance schedule $5,685 $8,880 $5,685
126,319
kWh
-
04 2.2163: Use minimum steam operating pressure $908 - - $908
-
MMBtu
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,013 - $2,013
44,842
kWh
-
06 2.7111: Reduce illumination to minimum necessary levels $1,336 - $1,336
29,601
kWh
-
07 2.4231: Reduce the pressure of compressed air to the minimum required $966 - $966
21,395
kWh
-
08 2.2136: Install / repair insulation on steam lines $305 $133 - $305
-
MMBtu
TOTAL RECOMMENDED $40,864 $21,805 $10,000
222,157
kWh
$30,864
-
MMBtu
TOTAL IMPLEMENTED $31,969 $12,925 $2,013
44,842
kWh
$29,956
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs