ITAC Assessment: TN0216
ITAC logo
ITAC Assessment: TN0216
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1984
Principal Product VACUUM CLEANERS
NAICS
n/a
SIC 3635: Household Vacuum Cleaners
Sales Range $50
M
to 100
M
# of Employees 350
Plant Area
n/a
Annual Production 400,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $406,636 8,512,017
kWh
Natural Gas $106,021 23,931
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,541 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,186

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2414: Use waste heat from hot flue gases to preheat $3,564 $4,000 - $3,564
-
MMBtu
02 2.6232: Install set-back timers $8,300 - $8,300
173,212
kWh
-
03 2.2514: Cover open tanks $1,096 $75 - $1,096
-
MMBtu
04 2.2514: Cover open tanks $273 $75 - $273
-
MMBtu
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $774 - $774
16,120
kWh
-
06 2.2511: Insulate bare equipment $422 $53 $422
8,792
kWh
-
07 2.6212: Turn off equipment during breaks, reduce operating time $112 - $112
2,345
kWh
-
TOTAL RECOMMENDED $14,541 $4,203 $9,608
200,469
kWh
$4,933
-
MMBtu
TOTAL IMPLEMENTED $9,186 - $9,186
191,677
kWh
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs