Assessment Year | 1984 |
---|---|
Principal Product | MOULDING COMPOUNDS |
NAICS |
n/a
|
SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
Sales Range | $500 k to 1M |
# of Employees | 10 |
Plant Area |
n/a
|
Annual Production | 700,000
lb
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $27,939 | 430,832 |
kWh
|
$0.065 |
Natural Gas | $22,049 | 4,291 |
MMBtu
|
$5.14 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $7,715 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,836 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,637 | $100 | - |
$3,937
-
MMBtu
|
$(-300.0) | |
02 | 2.2136: Install / repair insulation on steam lines | $2,764 | $2,000 | - |
$2,764
-
MMBtu
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $879 | $2,780 |
$879
21,981
kWh
|
- | - | |
04 | 2.2122: Install / repair insulation on condensate lines | $189 | $70 | - |
$189
-
MMBtu
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $246 | $20 |
$246
6,155
kWh
|
- | - | |
TOTAL RECOMMENDED | $7,715 | $4,970 |
$1,125
28,136
kWh
|
$6,890
-
MMBtu
|
$(-300.0) | ||
TOTAL IMPLEMENTED | $6,836 | $2,190 |
$246
6,155
kWh
|
$6,890
-
MMBtu
|
$(-300.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs