ITAC Assessment: TN0187
ITAC logo
ITAC Assessment: TN0187
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product CRUSHED ROCK AND SAND
NAICS
n/a
SIC 3281: Cut Stone and Stone Products
Sales Range $1
M
to 5
M
# of Employees 27
Plant Area
n/a
Annual Production 269,280
ton
Production Hrs. Annual 2,080
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $180,971 2,417,057
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $(-12,595.0) *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.3134: Shift from daytime to nighttime operation $(-14,400.0) $10,000 $9,900
-
kWh
$(-24,300.0)
02 2.6122: Adjust vents to minimize energy use $1,540 - $1,540
30,774
kWh
-
03 2.5121: Redesign flow to minimize mass transfer length $265 - $265
5,275
kWh
-
TOTAL RECOMMENDED $(-12,595.0) $10,000 $11,705
36,049
kWh
$(-24,300.0)
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs