ITAC Assessment: TN0183
ITAC logo
ITAC Assessment: TN0183
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product HOISERY & SLIPPER SOCKS
NAICS
n/a
SIC 2252: Hosiery, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 175
Plant Area
n/a
Annual Production 900,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $93,126 1,753,224
kWh
Natural Gas $121,630 23,354
MMBtu
Fuel Oil #2 $16,674 2,223
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $27,093 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $25,825

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Natural Gas Savings Fuel Oil #2 Savings Administrative Changes Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $12,515 $527 $11,440
-
MMBtu
$1,575
-
MMBtu
$(-500.0)
02 2.2441: Preheat boiler makeup water with waste process heat $9,500 $5,000 $8,350
-
MMBtu
$1,150
-
MMBtu
-
03 2.2136: Install / repair insulation on steam lines $3,810 $2,000 $3,350
-
MMBtu
$460
-
MMBtu
-
04 2.2511: Insulate bare equipment $1,268 $1,790 $1,115
-
MMBtu
$153
-
MMBtu
-
TOTAL RECOMMENDED $27,093 $9,317 $24,255
-
MMBtu
$3,338
-
MMBtu
$(-500.0)
TOTAL IMPLEMENTED $25,825 $7,527 $23,140
-
MMBtu
$3,185
-
MMBtu
$(-500.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs