ITAC Assessment: TN0169
ITAC logo
ITAC Assessment: TN0169
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product BOATS
NAICS
n/a
SIC 3732: Boat Building and Repairing
Sales Range $10
M
to 50
M
# of Employees 320
Plant Area
n/a
Annual Production 2,300
pieces
Production Hrs. Annual 2,200
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $108,564 2,072,099
kWh
Natural Gas $34,880 8,534
MMBtu
Fuel Oil #2 $32,594 4,626
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,800 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Natural Gas Savings Fuel Oil #2 Savings
01 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle $5,500 $50,000 $5,500
-
MMBtu
-
02 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle $800 - $800
-
MMBtu
-
03 2.2444: Use hot process fluids to preheat incoming process fluids $2,500 - $1,000
-
MMBtu
$1,500
-
MMBtu
TOTAL RECOMMENDED $8,800 $50,000 $7,300
-
MMBtu
$1,500
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs