| Assessment Year | 1983 |
|---|---|
| Principal Product | PISTONS |
| NAICS |
n/a
|
| SIC | 3592: Carburetors, Pistons, Piston Rings, and Valves |
| Sales Range | n/a |
| # of Employees | 350 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 0
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $555,902 | 12,728,019 |
kWh
|
$0.044 |
| Natural Gas | $96,970 | 23,454 |
MMBtu
|
$4.13 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $25,850 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7492: Use proper thickness of insulation on building envelope | $3,800 | $21,000 |
$3,800
93,787
kWh
|
- | |
| 02 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $12,600 | $25,000 | - |
$12,600
-
MMBtu
|
|
| 03 | 2.2414: Use waste heat from hot flue gases to preheat | $9,450 | $10,000 | - |
$9,450
-
MMBtu
|
|
| TOTAL RECOMMENDED | $25,850 | $56,000 |
$3,800
93,787
kWh
|
$22,050
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs