ITAC Assessment: TN0136
ITAC logo
ITAC Assessment: TN0136
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product INSULATORS
NAICS
n/a
SIC 3264: Porcelain Electrical Supplies
Sales Range $5
M
to 10
M
# of Employees 120
Plant Area
n/a
Annual Production 2,500,000
pieces
Production Hrs. Annual 0
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $51,884 1,208,089
kWh
Natural Gas $157,185 35,109
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,279 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $2,680 - $2,680
-
kWh
-
02 2.4133: Use most efficient type of electric motors $284 $160 $284
6,741
kWh
-
03 2.7421: Reduce glazed areas in buildings $315 $1,000 - $315
-
MMBtu
TOTAL RECOMMENDED $3,279 $1,160 $2,964
6,741
kWh
$315
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs