Assessment Year | 1996 |
---|---|
Principal Product | hydraulic articulating cranes and truck bodies |
NAICS |
n/a
|
SIC | 3536: Overhead Traveling Cranes, Hoists, and Monorail Systems |
Sales Range | $50 M to 100M |
# of Employees | 380 |
Plant Area |
300,000
ft2
|
Annual Production | 13,060
pieces
|
Production Hrs. Annual | 4,335
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $127,688 | 5,270,223 |
kWh
|
$0.024 |
Electricity Demand | $154,175 | 10,500 |
kW-mo/yr
|
$14.68 |
Natural Gas | $81,533 | 31,390 |
MMBtu
|
$2.60 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $25,764 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,129 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,243 | $213 |
$2,822
117,526
kWh
|
$3,421
-
kW-mo/yr
|
- | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,287 | $25 |
$399
16,706
kWh
|
$888
-
kW-mo/yr
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,887 | $15,222 |
$1,692
70,633
kWh
|
$1,195
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,123 | $2,510 |
$956
39,859
kWh
|
$1,167
-
kW-mo/yr
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,266 | $35,668 |
$2,832
118,113
kWh
|
$3,434
-
kW-mo/yr
|
- | - | |
06 | 2.7135: Install occupancy sensors | $1,124 | $4,081 |
$606
25,205
kWh
|
$518
-
kW-mo/yr
|
- | - | |
07 | 2.4133: Use most efficient type of electric motors | $210 | $480 |
$88
3,517
kWh
|
$122
-
kW-mo/yr
|
- | - | |
08 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $5,030 | $5,000 | - | - | - | $5,030 | |
09 | 3.1191: Change procedures / equipment / operating conditions | $594 | $2,900 | - | - |
$594
-
lb
|
- | |
TOTAL RECOMMENDED | $25,764 | $66,099 |
$9,395
391,559
kWh
|
$10,745
-
kW-mo/yr
|
$594
-
lb
|
$5,030 | ||
TOTAL IMPLEMENTED | $16,129 | $38,896 |
$7,097
295,721
kWh
|
$9,032
-
kW-mo/yr
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs