ITAC Assessment: TN0131
ITAC logo
ITAC Assessment: TN0131
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product FRESH PASTERIES
NAICS
n/a
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $10
M
to 50
M
# of Employees 220
Plant Area
n/a
Annual Production 20,000,000
lb
Production Hrs. Annual 5,270
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $75,092 1,922,333
kWh
Natural Gas $99,399 25,257
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,005 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2136: Install / repair insulation on steam lines $10,264 $3,000 - $10,264
-
MMBtu
02 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $1,109 $2,700 $1,109
28,429
kWh
-
03 2.2437: Recover waste heat from equipment $632 $2,800 - $632
-
MMBtu
TOTAL RECOMMENDED $12,005 $8,500 $1,109
28,429
kWh
$10,896
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs