Assessment Year | 1982 |
---|---|
Principal Product | SOLID-FUEL HEATERS |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | n/a |
# of Employees | 400 |
Plant Area |
n/a
|
Annual Production | 65,000
pieces
|
Production Hrs. Annual | 0
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $71,774 | 1,620,164 |
kWh
|
$0.044 |
Natural Gas | $96,211 | 31,221 |
MMBtu
|
$3.08 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $3,204 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2211: Use optimum temperature | $1,593 | - | - |
$1,593
-
MMBtu
|
|
02 | 2.2514: Cover open tanks | $467 | $900 | - |
$467
-
MMBtu
|
|
03 | 2.7141: Lower light fixtures in high ceiling areas | $663 | $800 |
$663
14,947
kWh
|
- | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $481 | $82 | - |
$481
-
MMBtu
|
|
TOTAL RECOMMENDED | $3,204 | $1,782 |
$663
14,947
kWh
|
$2,541
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs