ITAC Assessment: TN0119
ITAC logo
ITAC Assessment: TN0119
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product KNIT CLOTHING
NAICS
n/a
SIC 2322: Men's and Boys' Underwear and Nightwear
Sales Range $10
M
to 50
M
# of Employees 450
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 2,000
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $85,517 2,029,015
kWh
Natural Gas $253,031 86,043
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,224 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $7,158 $100 - $7,158
-
MMBtu
02 2.2441: Preheat boiler makeup water with waste process heat $3,150 $2,500 - $3,150
-
MMBtu
03 2.7142: Utilize higher efficiency lamps and/or ballasts $916 $1,300 $916
21,688
kWh
-
TOTAL RECOMMENDED $11,224 $3,900 $916
21,688
kWh
$10,308
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs