| Assessment Year | 1982 |
|---|---|
| Principal Product | RAILCARS |
| NAICS |
n/a
|
| SIC | 3743: Railroad Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
n/a
|
| Annual Production | 400
pieces
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $104,000 | 2,779,895 |
kWh
|
$0.037 |
| LPG | $34,000 | 5,404 |
MMBtu
|
$6.29 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $6,449 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings |
|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,760 | $500 | - |
$4,760
-
MMBtu
|
|
| 02 | 2.6218: Turn off equipment when not in use | $1,377 | - |
$160
2,931
kWh
|
$1,217
-
MMBtu
|
|
| 03 | 2.1321: Replace fossil fuel equipment with electrical equipment | $312 | - |
$(-6,600.0)
(-249,121)
kWh
|
$6,912
-
MMBtu
|
|
| TOTAL RECOMMENDED | $6,449 | $500 |
$(-6,440.0)
(-246,190)
kWh
|
$12,889
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs