ITAC Assessment: TA0118
ITAC logo
ITAC Assessment: TA0118
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Automotive Rubber, Plastic Products
NAICS 326291: Rubber Product Manufacturing for Mechanical Use
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 23
Plant Area 25,000
ft2
Annual Production 2,500,000
bbl
Production Hrs. Annual 2,286
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $45,610 329,800
kWh
Electricity Demand $9,108 1,564
kW-mo/yr
Natural Gas $5,168 402
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,241 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,100

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,339 $2,016 $1,855
18,059
kWh
$484
-
kW-mo/yr
02 2.7447: Install vinyl strip / high speed / air curtain doors $1,842 $2,000 $1,842
17,937
kWh
-
03 2.7447: Install vinyl strip / high speed / air curtain doors $141 $141 $141
5
kWh
-
04 2.7111: Reduce illumination to minimum necessary levels $1,049 $90 $483
21,068
kWh
$566
-
kW-mo/yr
05 2.4235: Remove or close off unneeded compressed air lines $520 - $160
1,532
kWh
$360
-
kW-mo/yr
06 2.4231: Reduce the pressure of compressed air to the minimum required $350 - $280
2,708
kWh
$70
-
kW-mo/yr
TOTAL RECOMMENDED $6,241 $4,247 $4,761
61,309
kWh
$1,480
-
kW-mo/yr
TOTAL IMPLEMENTED $6,100 $4,106 $4,620
61,304
kWh
$1,480
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs