| Assessment Year | 2006 |
|---|---|
| Principal Product | Automotive Rubber, Plastic Products |
| NAICS | 326291: Rubber Product Manufacturing for Mechanical Use |
| SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 23 |
| Plant Area |
25,000
ft2
|
| Annual Production | 2,500,000
bbl
|
| Production Hrs. Annual | 2,286
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $45,610 | 329,800 |
kWh
|
$0.14 |
| Electricity Demand | $9,108 | 1,564 |
kW-mo/yr
|
$5.82 |
| Natural Gas | $5,168 | 402 |
MMBtu
|
$12.86 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $6,241 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,100 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,339 | $2,016 |
$1,855
18,059
kWh
|
$484
-
kW-mo/yr
|
|
| 02 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,842 | $2,000 |
$1,842
17,937
kWh
|
- | |
| 03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $141 | $141 |
$141
5
kWh
|
- | |
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $1,049 | $90 |
$483
21,068
kWh
|
$566
-
kW-mo/yr
|
|
| 05 | 2.4235: Remove or close off unneeded compressed air lines | $520 | - |
$160
1,532
kWh
|
$360
-
kW-mo/yr
|
|
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $350 | - |
$280
2,708
kWh
|
$70
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $6,241 | $4,247 |
$4,761
61,309
kWh
|
$1,480
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $6,100 | $4,106 |
$4,620
61,304
kWh
|
$1,480
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs