Assessment Year | 2005 |
---|---|
Principal Product | paperboard boxes |
NAICS | 322212: Folding Paperboard Box Manufacturing |
SIC | 2657: Folding Paperboard Boxes, Including Sanitary |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
177,000
ft2
|
Annual Production | 40,000
ton
|
Production Hrs. Annual | 6,024
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $387,663 | 6,098,001 |
kWh
|
$0.064 |
Electricity Demand | $87,488 | 14,792 |
kW-mo/yr
|
$5.91 |
Natural Gas | $11,313 | 1,267 |
MMBtu
|
$8.93 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $35,077 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $23,677 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $11,100 | $22,000 | - |
$11,100
-
kW-mo/yr
|
- | |
02 | 2.2511: Insulate bare equipment | $2,910 | $495 |
$1,960
34,215
kWh
|
- |
$950
-
MMBtu
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,647 | $120 |
$1,402
23,728
kWh
|
$245
-
kW-mo/yr
|
- | |
04 | 2.6218: Turn off equipment when not in use | $1,590 | - |
$1,590
26,968
kWh
|
- | - | |
05 | 2.2212: Use minimum safe oven ventilation | $300 | - |
$300
5,041
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,530 | $11,050 |
$14,900
252,465
kWh
|
$2,630
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $35,077 | $33,665 |
$20,152
342,417
kWh
|
$13,975
-
kW-mo/yr
|
$950
-
MMBtu
|
||
TOTAL IMPLEMENTED | $23,677 | $11,665 |
$19,852
337,376
kWh
|
$2,875
-
kW-mo/yr
|
$950
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs