ITAC Assessment: TA0103
ITAC logo
ITAC Assessment: TA0103
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Injection molded plastics
NAICS 333511: Industrial Mold Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 90
Plant Area 63,000
ft2
Annual Production 3,000,000
lb
Production Hrs. Annual 6,408
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $356,037 4,785,200
kWh
Electricity Demand $87,111 11,960
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $32,628 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,168

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7228: Avoid introducing hot, humid, or dirty air into hvac system $12,460 $8,170 $12,460
165,050
kWh
-
02 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $1,365 $2,620 $1,365
18,067
kWh
-
03 2.7121: Utilize daylight whenever possible in lieu of artificial light $14,113 - $14,113
186,925
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,990 - $3,390
44,856
kWh
$600
-
kW-mo/yr
05 2.4235: Remove or close off unneeded compressed air lines $700 $1,070 $700
9,320
kWh
-
TOTAL RECOMMENDED $32,628 $11,860 $32,028
424,218
kWh
$600
-
kW-mo/yr
TOTAL IMPLEMENTED $20,168 $3,690 $19,568
259,168
kWh
$600
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs