Assessment Year | 2010 |
---|---|
Principal Product | Dry Packaged Foods |
NAICS | 311423: Dried and Dehydrated Food Manufacturing |
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | less than $500 k |
# of Employees | 531 |
Plant Area |
668,567
ft2
|
Annual Production | 299,396,499
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Delaware |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $4,197,946 | 43,302,360 |
kWh
|
$0.097 |
Electricity Demand | $536,875 | 7,158 |
kW-mo/yr
|
$75.00 |
Natural Gas | $80,974 | 15,446 |
MMBtu
|
$5.24 |
Coal | $1,476,972 | 106,550 |
MMBtu
|
$13.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,372,811 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $604,516 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Coal Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $39,401 | $83 |
$36,551
332
kWh
|
$2,850
-
kW-mo/yr
|
- | - | |
02 | 2.2153: Close off unneeded steam lines | $8,876 | $415 | - | - |
$8,876
-
MMBtu
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $143,083 | $15,941 |
$128,608
1
kWh
|
$14,475
-
kW-mo/yr
|
- | - | |
04 | 2.2136: Install / repair insulation on steam lines | $10,305 | $2,960 | - | - |
$10,305
-
MMBtu
|
- | |
05 | 2.2113: Repair or replace steam traps | $413,326 | $133,000 | - | - |
$413,326
-
MMBtu
|
- | |
06 | 2.4131: Size electric motors for peak operating efficiency | $38,896 | $22,745 |
$38,896
353,464
kWh
|
- | - | - | |
07 | 2.7314: Reduce ventilation air | $28,926 | $30,000 |
$4,196
38,148
kWh
|
- |
$24,730
-
MMBtu
|
- | |
08 | 2.1392: Replace purchased steam with other energy source | $430,429 | $460,000 | - | - | - | $430,429 | |
09 | 2.2437: Recover waste heat from equipment | $88,954 | $200,000 | - | - |
$88,954
-
MMBtu
|
- | |
10 | 2.5111: Convert from indirect to direct fired systems | $170,615 | $510,000 | - | - |
$170,615
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $1,372,811 | $1,375,144 |
$208,251
391,945
kWh
|
$17,325
-
kW-mo/yr
|
$716,806
-
MMBtu
|
$430,429 | ||
TOTAL IMPLEMENTED | $604,516 | $182,316 |
$132,804
38,149
kWh
|
$14,475
-
kW-mo/yr
|
$457,237
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Coal Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs