Assessment Year | 2004 |
---|---|
Principal Product | Aluminum Cans |
NAICS | 332431: Metal Can Manufacturing |
SIC | 3411: Metal Cans |
Sales Range | $50 M to 100M |
# of Employees | 105 |
Plant Area |
160,000
ft2
|
Annual Production | 1,000,000,000
pieces
|
Production Hrs. Annual | 8,592
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,319,693 | 32,459,284 |
kWh
|
$0.041 |
Electricity Demand | $267,342 | 55,192 |
kW-mo/yr
|
$4.84 |
Electricity Fees | $5,768 | - |
|
- |
Natural Gas | $427,895 | 75,701 |
MMBtu
|
$5.65 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $148,110 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $148,110 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1211: Move boiler to more efficient location | $87,420 | $4,860 | - | - |
$87,420
-
MMBtu
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $45,060 | $540 |
$37,900
929,390
kWh
|
$7,160
-
kW-mo/yr
|
- | |
03 | 2.2511: Insulate bare equipment | $10,000 | $3,200 | - | - |
$10,000
-
MMBtu
|
|
04 | 2.2212: Use minimum safe oven ventilation | $1,890 | $1,500 | - | - |
$1,890
-
MMBtu
|
|
05 | 2.7124: Make a practice of turning off lights when not needed | $3,740 | - |
$3,740
91,610
kWh
|
- | - | |
TOTAL RECOMMENDED | $148,110 | $10,100 |
$41,640
1,021,000
kWh
|
$7,160
-
kW-mo/yr
|
$99,310
-
MMBtu
|
||
TOTAL IMPLEMENTED | $148,110 | $10,100 |
$41,640
1,021,000
kWh
|
$7,160
-
kW-mo/yr
|
$99,310
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs