ITAC Assessment: TA0085
ITAC logo
ITAC Assessment: TA0085
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product PEY plastic bottles
NAICS 326160: Plastics Bottle Manufacturing
SIC 3085: Plastics Bottles
Sales Range $50
M
to 100
M
# of Employees 150
Plant Area 225,000
ft2
Annual Production 720,000,000
pieces
Production Hrs. Annual 8,700
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,341,735 23,113,426
kWh
Electricity Demand $178,483 38,136
kW-mo/yr
Electricity Fees $2,308 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,202,663 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,147,633

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings
01 3.1191: Change procedures / equipment / operating conditions $1,138,683 - - - $1,138,683
-
Tgal
02 2.4323: Use optimum size and capacity equipment $37,330 $30,000 $32,960
574,200
kWh
$4,370
-
kW-mo/yr
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $17,700 $36,000 $15,650
272,650
kWh
$2,050
-
kW-mo/yr
-
04 2.6218: Turn off equipment when not in use $6,840 - $6,840
119,160
kWh
- -
05 2.7124: Make a practice of turning off lights when not needed $2,110 - $2,110
36,775
kWh
- -
TOTAL RECOMMENDED $1,202,663 $66,000 $57,560
1,002,785
kWh
$6,420
-
kW-mo/yr
$1,138,683
-
Tgal
TOTAL IMPLEMENTED $1,147,633 - $8,950
155,935
kWh
- $1,138,683
-
Tgal
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs