Assessment Year | 2004 |
---|---|
Principal Product | Polystyrene Egg Cartons |
NAICS | 326140: Polystyrene Foam Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
135,000
ft2
|
Annual Production | 67,000,000
pieces
|
Production Hrs. Annual | 7,296
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $732,220 | 16,602,288 |
kWh
|
$0.044 |
Electricity Demand | $134,599 | 28,736 |
kW-mo/yr
|
$4.68 |
Electricity Fees | $3,161 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $121,461 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $42,038 | - |
$42,038
654,372
kWh
|
- | |
02 | 2.2511: Insulate bare equipment | $25,800 | $2,070 |
$24,370
379,336
kWh
|
$1,430
-
kW-mo/yr
|
|
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $25,680 | $25 |
$25,680
399,700
kWh
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $11,500 | $370 |
$10,300
160,433
kWh
|
$1,200
-
kW-mo/yr
|
|
05 | 2.6218: Turn off equipment when not in use | $5,350 | - |
$4,690
72,960
kWh
|
$660
-
kW-mo/yr
|
|
06 | 2.2511: Insulate bare equipment | $4,670 | $910 |
$4,670
72,692
kWh
|
- | |
07 | 2.6218: Turn off equipment when not in use | $3,263 | - |
$3,263
50,800
kWh
|
- | |
08 | 2.7124: Make a practice of turning off lights when not needed | $3,160 | - |
$3,160
49,193
kWh
|
- | |
TOTAL RECOMMENDED | $121,461 | $3,375 |
$118,171
1,839,486
kWh
|
$3,290
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs