| Assessment Year | 2003 |
|---|---|
| Principal Product | Candy and Nuts for Ice Cream |
| NAICS | 311340: Nonchocolate Confectionery Manufacturing |
| SIC | 2064: Candy and Other Confectionery Products |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
70,000
ft2
|
| Annual Production | 28,666,600
lb
|
| Production Hrs. Annual | 6,336
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $171,685 | 3,986,340 |
kWh
|
$0.043 |
| Electricity Demand | $62,339 | 8,217 |
kW-mo/yr
|
$7.59 |
| Electricity Fees | $6,367 | - |
|
- |
| Natural Gas | $111,889 | 16,053 |
MMBtu
|
$6.97 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $845,500 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $20,570 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 4.441: Install automatic packing equipment | $823,680 | $180,000 | - | - | - | $823,680 | |
| 02 | 2.3132: Recharge batteries on during off-peak demand periods | $12,100 | - | - |
$12,100
-
kW-mo/yr
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,175 | $5,783 |
$3,055
84,097
kWh
|
$2,120
-
kW-mo/yr
|
- | - | |
| 04 | 2.6218: Turn off equipment when not in use | $1,400 | - |
$1,400
38,850
kWh
|
- | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,300 | $72 |
$680
18,780
kWh
|
$620
-
kW-mo/yr
|
- | - | |
| 06 | 2.2136: Install / repair insulation on steam lines | $550 | $175 | - | - |
$550
-
MMBtu
|
- | |
| 07 | 2.2511: Insulate bare equipment | $460 | $336 | - | - |
$460
-
MMBtu
|
- | |
| 08 | 2.7135: Install occupancy sensors | $275 | $180 |
$275
7,527
kWh
|
- | - | - | |
| 09 | 2.2122: Install / repair insulation on condensate lines | $240 | $110 | - | - |
$240
-
MMBtu
|
- | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $200 | $395 |
$140
3,925
kWh
|
$60
-
kW-mo/yr
|
- | - | |
| 11 | 2.6218: Turn off equipment when not in use | $120 | - | - | - |
$120
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $845,500 | $187,051 |
$5,550
153,179
kWh
|
$14,900
-
kW-mo/yr
|
$1,370
-
MMBtu
|
$823,680 | ||
| TOTAL IMPLEMENTED | $20,570 | $6,430 |
$5,550
153,179
kWh
|
$14,900
-
kW-mo/yr
|
$120
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs