| Assessment Year | 2002 |
|---|---|
| Principal Product | Corrugated Boxes |
| NAICS |
n/a
|
| SIC | 2653: Corrugated and Solid Fiber Boxes |
| Sales Range | $50 M to 100M |
| # of Employees | 205 |
| Plant Area |
190,000
ft2
|
| Annual Production | 1,200,000
thousand feet
|
| Production Hrs. Annual | 6,552
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $268,563 | 5,956,125 |
kWh
|
$0.045 |
| Electricity Demand | $107,738 | 13,134 |
kW-mo/yr
|
$8.20 |
| Electricity Fees | $27,655 | - |
|
- |
| Natural Gas | $289,760 | 49,904 |
MMBtu
|
$5.81 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $71,885 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $22,795 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2414: Use waste heat from hot flue gases to preheat | $48,270 | $20,000 | - | - |
$48,270
-
MMBtu
|
|
| 02 | 2.7124: Make a practice of turning off lights when not needed | $8,290 | - |
$8,290
150,820
kWh
|
- | - | |
| 03 | 2.2136: Install / repair insulation on steam lines | $5,620 | $1,210 | - | - |
$5,620
-
MMBtu
|
|
| 04 | 2.4239: Eliminate or reduce compressed air usage | $5,450 | $40 |
$4,700
85,540
kWh
|
$750
-
kW-mo/yr
|
- | |
| 05 | 2.2135: Repair and eliminate steam leaks | $2,620 | $300 | - | - |
$2,620
-
MMBtu
|
|
| 06 | 2.7124: Make a practice of turning off lights when not needed | $820 | - |
$820
14,876
kWh
|
- | - | |
| 07 | 2.7135: Install occupancy sensors | $815 | $180 |
$815
14,840
kWh
|
- | - | |
| TOTAL RECOMMENDED | $71,885 | $21,730 |
$14,625
266,076
kWh
|
$750
-
kW-mo/yr
|
$56,510
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $22,795 | $1,730 |
$13,805
251,200
kWh
|
$750
-
kW-mo/yr
|
$8,240
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs