ITAC Assessment: TA0040
ITAC logo
ITAC Assessment: TA0040
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Ready Mix Concrete
NAICS
n/a
SIC 3273: Ready-Mixed Concrete
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 42,900
ft2
Annual Production 4,170
thousand feet
Production Hrs. Annual 2,522
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $23,499 376,098
kWh
Electricity Demand $10,019 1,567
kW-mo/yr
Electricity Fees $5,709 -
Natural Gas $6,211 1,017
MMBtu
Fuel Oil #1 $28,241 37,209
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $18,345 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,704

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Fuel Oil #1 Savings Water Consumption Savings
01 3.1175: Use a different or recycled raw material $11,200 $12,425 - - - - $11,200
-
Tgal
02 2.8121: Apply for tax-free status for energy purchases $2,952 - - - $2,952 - -
03 2.8226: Increase efficiency of trucks $2,552 - - - - $2,552
-
MMBtu
-
04 2.7121: Utilize daylight whenever possible in lieu of artificial light $1,210 - $1,210
41,000
kWh
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $181 $90 $62
2,115
kWh
$119
-
kW-mo/yr
- - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $140 - $45
1,580
kWh
$95
-
kW-mo/yr
- - -
07 2.7135: Install occupancy sensors $110 $130 $110
3,740
kWh
- - - -
TOTAL RECOMMENDED $18,345 $12,645 $1,427
48,435
kWh
$214
-
kW-mo/yr
$2,952 $2,552
-
MMBtu
$11,200
-
Tgal
TOTAL IMPLEMENTED $16,704 $12,425 - - $2,952 $2,552
-
MMBtu
$11,200
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Fuel Oil #1 Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs