| Assessment Year | 2002 |
|---|---|
| Principal Product | Ready Mix Concrete |
| NAICS |
n/a
|
| SIC | 3273: Ready-Mixed Concrete |
| Sales Range | $10 M to 50M |
| # of Employees | 80 |
| Plant Area |
42,900
ft2
|
| Annual Production | 4,170
thousand feet
|
| Production Hrs. Annual | 2,522
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $23,499 | 376,098 |
kWh
|
$0.062 |
| Electricity Demand | $10,019 | 1,567 |
kW-mo/yr
|
$6.39 |
| Electricity Fees | $5,709 | - |
|
- |
| Natural Gas | $6,211 | 1,017 |
MMBtu
|
$6.11 |
| Fuel Oil #1 | $28,241 | 37,209 |
MMBtu
|
$0.76 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,345 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $16,704 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Fuel Oil #1 Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.1175: Use a different or recycled raw material | $11,200 | $12,425 | - | - | - | - |
$11,200
-
Tgal
|
|
| 02 | 2.8121: Apply for tax-free status for energy purchases | $2,952 | - | - | - | $2,952 | - | - | |
| 03 | 2.8226: Increase efficiency of trucks | $2,552 | - | - | - | - |
$2,552
-
MMBtu
|
- | |
| 04 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,210 | - |
$1,210
41,000
kWh
|
- | - | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $181 | $90 |
$62
2,115
kWh
|
$119
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $140 | - |
$45
1,580
kWh
|
$95
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.7135: Install occupancy sensors | $110 | $130 |
$110
3,740
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $18,345 | $12,645 |
$1,427
48,435
kWh
|
$214
-
kW-mo/yr
|
$2,952 |
$2,552
-
MMBtu
|
$11,200
-
Tgal
|
||
| TOTAL IMPLEMENTED | $16,704 | $12,425 | - | - | $2,952 |
$2,552
-
MMBtu
|
$11,200
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Fuel Oil #1 Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs