| Assessment Year | 2002 |
|---|---|
| Principal Product | Wire and Metal Display Products |
| NAICS |
n/a
|
| SIC | 3496: Miscellaneous Fabricated Wire Products |
| Sales Range | $5 M to 10M |
| # of Employees | 100 |
| Plant Area |
100,000
ft2
|
| Annual Production | 300,000
pieces
|
| Production Hrs. Annual | 2,570
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $61,075 | 1,020,567 |
kWh
|
$0.060 |
| Electricity Demand | $16,358 | 5,486 |
kW-mo/yr
|
$2.98 |
| Electricity Fees | $19,522 | - |
|
- |
| Natural Gas | $31,551 | 2,984 |
MMBtu
|
$10.57 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $33,243 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $31,623 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $19,125 | $7,500 | - | - | - | - |
$19,125
-
Tgal
|
|
| 02 | 2.8114: Change rate schedules or other changes in utility service | $6,660 | - | - | - | $6,660 | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,280 | $135 |
$2,630
40,970
kWh
|
$650
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,244 | $5 |
$2,244
34,938
kWh
|
- | - | - | - | |
| 05 | 2.7111: Reduce illumination to minimum necessary levels | $980 | $30 |
$790
12,336
kWh
|
$190
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.7124: Make a practice of turning off lights when not needed | $640 | - |
$640
9,970
kWh
|
- | - | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $204 | $296 |
$190
2,940
kWh
|
$14
-
kW-mo/yr
|
- | - | - | |
| 08 | 2.2511: Insulate bare equipment | $110 | $100 | - | - | - |
$110
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $33,243 | $8,066 |
$6,494
101,154
kWh
|
$854
-
kW-mo/yr
|
$6,660 |
$110
-
MMBtu
|
$19,125
-
Tgal
|
||
| TOTAL IMPLEMENTED | $31,623 | $8,036 |
$5,064
78,848
kWh
|
$664
-
kW-mo/yr
|
$6,660 |
$110
-
MMBtu
|
$19,125
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs