Assessment Year | 2002 |
---|---|
Principal Product | Automotive Sub-Assembly |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $10 M to 50M |
# of Employees | 539 |
Plant Area |
500,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,072
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $323,713 | 7,422,300 |
kWh
|
$0.044 |
Electricity Demand | $116,827 | 14,316 |
kW-mo/yr
|
$8.16 |
Electricity Fees | $81,633 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $113,965 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $113,065 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.5316: Contract a wood pallet recycling company | $39,000 | - | - | - | - |
$39,000
-
Tgal
|
|
02 | 2.8121: Apply for tax-free status for energy purchases | $37,007 | - | - | - | $37,007 | - | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $28,990 | $900 |
$17,590
466,329
kWh
|
$11,400
-
kW-mo/yr
|
- | - | |
04 | 2.8123: Pay utility bills on time | $7,678 | - | - | - | $7,678 | - | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $900 | $55 |
$550
14,570
kWh
|
$350
-
kW-mo/yr
|
- | - | |
06 | 2.7135: Install occupancy sensors | $390 | $256 |
$390
10,300
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $113,965 | $1,211 |
$18,530
491,199
kWh
|
$11,750
-
kW-mo/yr
|
$44,685 |
$39,000
-
Tgal
|
||
TOTAL IMPLEMENTED | $113,065 | $1,156 |
$17,980
476,629
kWh
|
$11,400
-
kW-mo/yr
|
$44,685 |
$39,000
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs