ITAC Assessment: TA0026
ITAC logo
ITAC Assessment: TA0026
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Lamp Bases and Leads
NAICS
n/a
SIC 3641: Electric Lamp Bulbs and Tubes
Sales Range $10
M
to 50
M
# of Employees 93
Plant Area 110,000
ft2
Annual Production 12,000,000,000
pieces
Production Hrs. Annual 6,296
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $216,977 5,028,480
kWh
Electricity Demand $66,858 8,971
kW-mo/yr
Electricity Fees $25,471 -
Natural Gas $44,486 59,778
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,889 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,659

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,400 $1,120 $4,400
124,000
kWh
- -
02 2.7494: Install storm windows and doors $1,690 $230 - - $1,690
-
MMBtu
03 2.6212: Turn off equipment during breaks, reduce operating time $1,230 - $1,230
34,342
kWh
- -
04 2.2511: Insulate bare equipment $980 $400 - - $980
-
MMBtu
05 2.7135: Install occupancy sensors $875 $346 $875
24,425
kWh
- -
06 2.3132: Recharge batteries on during off-peak demand periods $500 - - $500
-
kW-mo/yr
-
07 2.7292: Lower ceiling to reduce conditioned space $214 - - - $214
-
MMBtu
TOTAL RECOMMENDED $9,889 $2,096 $6,505
182,767
kWh
$500
-
kW-mo/yr
$2,884
-
MMBtu
TOTAL IMPLEMENTED $8,659 $2,096 $5,275
148,425
kWh
$500
-
kW-mo/yr
$2,884
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs