ITAC Assessment: TA0023
ITAC logo
ITAC Assessment: TA0023
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Paper Envelopes
NAICS
n/a
SIC 2677: Envelopes
Sales Range $10
M
to 50
M
# of Employees 240
Plant Area 250,000
ft2
Annual Production 2,000,000,000
pieces
Production Hrs. Annual 6,192
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $457,099 9,263,376
kWh
Electricity Demand $89,737 22,310
kW-mo/yr
Electricity Fees $65,120 -
Natural Gas $56,465 6,083
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,336 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,036

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.8123: Pay utility bills on time $5,506 - - - $5,506
02 2.4314: Use synthetic lubricant $3,150 - $2,800
53,538
kWh
$350
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,150 - $1,685
32,273
kWh
$465
-
kW-mo/yr
-
04 2.7121: Utilize daylight whenever possible in lieu of artificial light $270 - $270
5,177
kWh
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $260 $468 $243
4,660
kWh
$17
-
kW-mo/yr
-
TOTAL RECOMMENDED $11,336 $468 $4,998
95,648
kWh
$832
-
kW-mo/yr
$5,506
TOTAL IMPLEMENTED $6,036 $468 $513
9,837
kWh
$17
-
kW-mo/yr
$5,506
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs