Assessment Year | 2001 |
---|---|
Principal Product | Industrial Paint Spray Booths and Finishing Systems |
NAICS |
n/a
|
SIC | 3444: Sheet Metal Work |
Sales Range | $10 M to 50M |
# of Employees | 135 |
Plant Area |
220,000
ft2
|
Annual Production | 300
units
|
Production Hrs. Annual | 2,680
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $62,442 | 1,480,000 |
kWh
|
$0.042 |
Electricity Demand | $41,195 | 5,096 |
kW-mo/yr
|
$8.08 |
Electricity Fees | $11,952 | - |
|
- |
Natural Gas | $6,139 | 1,071 |
MMBtu
|
$5.73 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $23,264 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,494 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $9,338 | $450 |
$2,977
114,490
kWh
|
$6,361
-
kW-mo/yr
|
- | |
02 | 2.8121: Apply for tax-free status for energy purchases | $8,612 | $(-8,612.0) | - | - | $8,612 | |
03 | 4.821: Pay bills on time to avoid late fees | $2,563 | - | - | - | $2,563 | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,094 | - |
$679
26,215
kWh
|
$1,415
-
kW-mo/yr
|
- | |
05 | 2.7132: Install timers on light switches in little used areas | $432 | $454 |
$432
16,610
kWh
|
- | - | |
06 | 2.7124: Make a practice of turning off lights when not needed | $225 | $90 |
$76
2,939
kWh
|
$149
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $23,264 | $(-7,618.0) |
$4,164
160,254
kWh
|
$7,925
-
kW-mo/yr
|
$11,175 | ||
TOTAL IMPLEMENTED | $13,494 | $(-8,522.0) |
$755
29,154
kWh
|
$1,564
-
kW-mo/yr
|
$11,175 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs