Assessment Year | 2025 |
---|---|
Principal Product | Pharmaceutical Compounds |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $10 M to 50M |
# of Employees | 154 |
Plant Area |
72,067
ft2
|
Annual Production | 8,000,000
units
|
Production Hrs. Annual | 3,380
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $41,078 | 2,027,487 |
kWh
|
$0.020 |
Electricity Demand | $58,895 | 3,561 |
kW-mo/yr
|
$16.54 |
Electricity Fees | $14,765 | - |
|
- |
Natural Gas | $10,107 | 1,641 |
MMBtu
|
$6.16 |
Other Gas | $927 | 1,641 |
MMBtu
|
$0.56 |
TOTAL YEARLY COSTS | $125,771 | |||
RECOMMENDED SAVINGS* | $16,848 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $21 | - |
$21
1,066
kWh
|
- | - | - | |
02 | 2.7122: Disconnect ballasts | $94 | - |
$24
1,190
kWh
|
$70
-
kW-mo/yr
|
- | - | |
03 | 4.821: Pay bills on time to avoid late fees | $530 | - | - | - | - | $530 | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,944 | - | - |
$2,944
-
kW-mo/yr
|
- | - | |
05 | 2.8121: Apply for tax-free status for energy purchases | $9,467 | $65 | - | - | - | $9,467 | |
06 | 2.4322: Use or replace with energy efficient substitutes | $808 | $43 |
$191
9,563
kWh
|
$868
-
kW-mo/yr
|
$(-251.2)
-
MMBtu
|
- | |
07 | 2.7224: Reduce space conditioning during non-working hours | $153 | $203 | - | - |
$153
-
MMBtu
|
- | |
08 | 2.6211: Conserve energy by efficient use of vending machines | $80 | $188 |
$80
3,986
kWh
|
- | - | - | |
09 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $28 | $100 |
$28
1,384
kWh
|
- | - | - | |
10 | 2.7135: Install occupancy sensors | $107 | $598 |
$107
5,357
kWh
|
- | - | - | |
11 | 2.7234: Use heat pump for space conditioning | $2,615 | $31,920 |
$(-756.9)
(-37,843)
kWh
|
- |
$3,372
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $16,848 | $33,116 |
$(-305.6)
(-15,298)
kWh
|
$3,882
-
kW-mo/yr
|
$3,273
-
MMBtu
|
$9,998 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs