ITAC Assessment: SU0571
ITAC logo
ITAC Assessment: SU0571
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Provide a full range of machining to aerospace customers
NAICS 336412: Aircraft Engine and Engine Parts Manufacturing
SIC 3724: Aircraft Engines and Engine Parts
Sales Range $10
M
to 50
M
# of Employees 135
Plant Area 87,936
ft2
Annual Production 95,000
units
Production Hrs. Annual 6,500
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $244,102 4,761,229
kWh
Electricity Demand $163,396 12,268
kW-mo/yr
Electricity Fees $16,340 -
Natural Gas $48,176 6,962
MMBtu
Other Gas $3,954 1
MMBtu
Waste Disposal Costs
Water Usage $100,000 5,600
Tgal
TOTAL YEARLY COSTS $575,967
RECOMMENDED SAVINGS* $140,392 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.7224: Reduce space conditioning during non-working hours $1,987 - - - $1,987
-
MMBtu
-
02 2.8121: Apply for tax-free status for energy purchases $2,187 - - - - $2,187
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $8,170 - - $8,170
-
kW-mo/yr
- -
04 2.4239: Eliminate or reduce compressed air usage $3,489 $632 $3,489
68,415
kWh
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,385 $320 $1,385
27,160
kWh
- - -
06 2.2437: Recover waste heat from equipment $512 $418 - - $512
-
MMBtu
-
07 2.7135: Install occupancy sensors $264 $824 $264
5,175
kWh
- - -
08 2.6211: Conserve energy by efficient use of vending machines $672 $2,129 $672
13,184
kWh
- - -
09 2.2511: Insulate bare equipment $166 $1,267 $166
3,253
kWh
- - -
10 2.9114: Use solar heat to make electricty $121,560 $1,856,682 $121,560
2,383,524
kWh
- - -
TOTAL RECOMMENDED $140,392 $1,862,272 $127,537
2,500,711
kWh
$8,170
-
kW-mo/yr
$2,499
-
MMBtu
$2,187
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs