ITAC Assessment: SU0550
ITAC logo
ITAC Assessment: SU0550
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Automated electronic equipment
NAICS 333249: Other Industrial Machinery Manufacturing
SIC 3559: Special Industry Machinery, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 240
Plant Area 248,000
ft2
Annual Production 144
units
Production Hrs. Annual 4,160
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $384,142 7,673,945
kWh
Electricity Demand $122,529 44,659
kW-mo/yr
Natural Gas $84,169 42,964
MMBtu
Waste Disposal Costs
Water Usage $41,000 2,674
Tgal
Solid Waste (non-haz) $20,000 2,000
lb
Solid Waste (haz) $850 100
lb
TOTAL YEARLY COSTS $652,691
RECOMMENDED SAVINGS* $58,164 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings One-time Revenue or Avoided Cost Savings
01 2.3132: Recharge batteries on during off-peak demand periods $2,161 - - $2,161
-
kW-mo/yr
- - -
02 2.4239: Eliminate or reduce compressed air usage $2,137 - $2,137
42,743
kWh
- - - -
03 2.7122: Disconnect ballasts $1,547 - $1,258
25,168
kWh
$289
-
kW-mo/yr
- - -
04 2.4322: Use or replace with energy efficient substitutes $2,721 $48 $2,025
40,500
kWh
$700
-
kW-mo/yr
$(-3.4)
-
MMBtu
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $758 $80 $758
15,162
kWh
- - - -
06 2.8121: Apply for tax-free status for energy purchases $237 $50 - - - - $237
07 2.7142: Utilize higher efficiency lamps and/or ballasts $129 $76 $96
1,927
kWh
$7
-
kW-mo/yr
- - $26
08 2.2136: Install / repair insulation on steam lines $77 $75 - - $77
-
MMBtu
- -
09 2.8227: Adjust / maintain fork lift trucks for most efficient operation $24,107 $24,000 $(-5,096.0)
(-101,920)
kWh
- - $29,203
-
MMBtu
-
10 2.7142: Utilize higher efficiency lamps and/or ballasts $9,192 $9,587 $6,246
124,924
kWh
$1,438
-
kW-mo/yr
- - $1,507
11 2.6211: Conserve energy by efficient use of vending machines $530 $847 $530
10,605
kWh
- - - -
12 2.9114: Use solar heat to make electricty $14,567 $156,925 $14,567
291,344
kWh
- - - -
TOTAL RECOMMENDED $58,164 $191,688 $22,522
450,453
kWh
$4,595
-
kW-mo/yr
$74
-
MMBtu
$29,203
-
MMBtu
$1,770
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs