ITAC Assessment: SU0497
ITAC logo
ITAC Assessment: SU0497
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Boron Nitride
NAICS 327910: Abrasive Product Manufacturing
SIC 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 46
Plant Area 94,000
ft2
Annual Production 322,000
lb
Production Hrs. Annual 8,424
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $297,240 37,349,972
kWh
Electricity Demand $606,131 102,039
kW-mo/yr
Electricity Fees $79,841 -
Natural Gas $108,700 23,943
MMBtu
Other Gas $3,613 89
MMBtu
Waste Disposal Costs
Water Usage $54,477 18,000,000
Tgal
TOTAL YEARLY COSTS $1,150,002
RECOMMENDED SAVINGS* $8,884 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,339

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $1,000 - $1,000
124,998
kWh
- - -
02 2.4322: Use or replace with energy efficient substitutes $327 $32 $414
51,744
kWh
$915
-
kW-mo/yr
$(-1,001.9)
-
MMBtu
-
03 2.2136: Install / repair insulation on steam lines $1,235 $257 - - $1,235
-
MMBtu
-
04 2.7224: Reduce space conditioning during non-working hours $177 $5,032 - - $177
-
MMBtu
-
05 2.7314: Reduce ventilation air $1,191 $882 $112
14,073
kWh
- $1,079
-
MMBtu
-
06 3.1161: Eliminate/reduce an operation $1,415 $1,857 $(-8.7)
1,083
kWh
$(-370.7)
-
kW-mo/yr
- $1,794
07 2.7142: Utilize higher efficiency lamps and/or ballasts $302 $510 $39
4,818
kWh
$39
-
kW-mo/yr
- $224
08 2.7142: Utilize higher efficiency lamps and/or ballasts $3,107 $51,554 $666
83,217
kWh
$1,176
-
kW-mo/yr
- $1,265
09 2.7135: Install occupancy sensors $131 $4,097 $131
16,326
kWh
- - -
TOTAL RECOMMENDED $8,884 $64,222 $2,353
296,259
kWh
$1,759
-
kW-mo/yr
$1,489
-
MMBtu
$3,283
TOTAL IMPLEMENTED $6,339 $58,268 $1,231
153,852
kWh
$2,130
-
kW-mo/yr
$1,489
-
MMBtu
$1,489
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs