ITAC Assessment: SU0452
ITAC logo
ITAC Assessment: SU0452
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Consumer Goods Paperboard Packaging
NAICS 322219: Other Paperboard Container Manufacturing
SIC 2611: Pulp Mills
Sales Range $100
M
to 500
M
# of Employees 450
Plant Area 606,781
ft2
Annual Production 1,548,729
pieces
Production Hrs. Annual 8,736
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $844,023 26,229,921
kWh
Electricity Demand $274,687 47,260
kW-mo/yr
Electricity Fees $1,118,710 -
Natural Gas $181,336 38,835
MMBtu
Waste Disposal Costs
Water Usage $10,657 4,053
Tgal
TOTAL YEARLY COSTS $2,429,413
RECOMMENDED SAVINGS* $48,906 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $46,795

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $4,109 - $3,288
102,755
kWh
$821
-
kW-mo/yr
- -
02 4.821: Pay bills on time to avoid late fees $2,111 - - - - $2,111
03 3.1161: Eliminate/reduce an operation $16,784 $4,317 $(-132.0)
(-4,140)
kWh
$(-418.0)
-
kW-mo/yr
$3,429 $13,905
04 2.7142: Utilize higher efficiency lamps and/or ballasts $347 $524 $137
4,293
kWh
$34
-
kW-mo/yr
$145 $31
05 2.4321: Upgrade obsolete equipment $25,555 $120,000 $25,555
798,610
kWh
- - -
TOTAL RECOMMENDED $48,906 $124,841 $28,848
901,518
kWh
$437
-
kW-mo/yr
$3,574 $16,047
TOTAL IMPLEMENTED $46,795 $124,841 $28,848
901,518
kWh
$437
-
kW-mo/yr
$3,574 $13,936
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs