ITAC Assessment: SU0449
ITAC logo
ITAC Assessment: SU0449
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Sodium bicarbonate
NAICS 325180: Other Basic Inorganic Chemical Manufacturing
SIC 2812: Alkalies and Chlorine
Sales Range $5
M
to 10
M
# of Employees 24
Plant Area 39,200
ft2
Annual Production 15,000
ton
Production Hrs. Annual 7,200
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $18,995 526,009
kWh
Electricity Demand $12,557 1,486
kW-mo/yr
Electricity Fees $1,878 -
Natural Gas $69,503 11,354
MMBtu
Waste Disposal Costs
Water Usage $7,850 22
Tgal
TOTAL YEARLY COSTS $110,782
RECOMMENDED SAVINGS* $8,917 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,895

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.2136: Install / repair insulation on steam lines $2,375 $267 - - $2,375
-
MMBtu
- -
02 3.1161: Eliminate/reduce an operation $1,271 $900 - - - - $1,271
03 2.7142: Utilize higher efficiency lamps and/or ballasts $194 $208 $82
2,050
kWh
$23
-
kW-mo/yr
- $89 -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,895 $3,697 $1,042
26,051
kWh
$548
-
kW-mo/yr
- $305 -
05 2.2414: Use waste heat from hot flue gases to preheat $3,182 $15,784 - - $3,182
-
MMBtu
- -
TOTAL RECOMMENDED $8,917 $20,856 $1,124
28,101
kWh
$571
-
kW-mo/yr
$5,557
-
MMBtu
$394 $1,271
TOTAL IMPLEMENTED $1,895 $3,697 $1,042
26,051
kWh
$548
-
kW-mo/yr
- $305 -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs