Assessment Year | 2017 |
---|---|
Principal Product | Sodium bicarbonate |
NAICS | 325180: Other Basic Inorganic Chemical Manufacturing |
SIC | 2812: Alkalies and Chlorine |
Sales Range | $5 M to 10M |
# of Employees | 24 |
Plant Area |
39,200
ft2
|
Annual Production | 15,000
ton
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $18,995 | 526,009 |
kWh
|
$0.036 | |
Electricity Demand | $12,557 | 1,486 |
kW-mo/yr
|
$8.45 | |
Electricity Fees | $1,878 | - |
|
- | |
Natural Gas | $69,503 | 11,354 |
MMBtu
|
$6.12 | |
Waste Disposal Costs | |||||
Water Usage | $7,850 | 22 |
Tgal
|
$363.43 | |
TOTAL YEARLY COSTS | $110,782 | ||||
RECOMMENDED SAVINGS* | $8,917 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $1,895 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2136: Install / repair insulation on steam lines | $2,375 | $267 | - | - |
$2,375
-
MMBtu
|
- | - | |
02 | 3.1161: Eliminate/reduce an operation | $1,271 | $900 | - | - | - | - | $1,271 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $194 | $208 |
$82
2,050
kWh
|
$23
-
kW-mo/yr
|
- | $89 | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,895 | $3,697 |
$1,042
26,051
kWh
|
$548
-
kW-mo/yr
|
- | $305 | - | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $3,182 | $15,784 | - | - |
$3,182
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $8,917 | $20,856 |
$1,124
28,101
kWh
|
$571
-
kW-mo/yr
|
$5,557
-
MMBtu
|
$394 | $1,271 | ||
TOTAL IMPLEMENTED | $1,895 | $3,697 |
$1,042
26,051
kWh
|
$548
-
kW-mo/yr
|
- | $305 | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs