| Assessment Year | 2017 |
|---|---|
| Principal Product | Sodium bicarbonate |
| NAICS | 325180: Other Basic Inorganic Chemical Manufacturing |
| SIC | 2812: Alkalies and Chlorine |
| Sales Range | $5 M to 10M |
| # of Employees | 24 |
| Plant Area |
39,200
ft2
|
| Annual Production | 15,000
ton
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $18,995 | 526,009 |
kWh
|
$0.036 | |
| Electricity Demand | $12,557 | 1,486 |
kW-mo/yr
|
$8.45 | |
| Electricity Fees | $1,878 | - |
|
- | |
| Natural Gas | $69,503 | 11,354 |
MMBtu
|
$6.12 | |
| Waste Disposal Costs | |||||
| Water Usage | $7,850 | 22 |
Tgal
|
$363.43 | |
| TOTAL YEARLY COSTS | $110,782 | ||||
| RECOMMENDED SAVINGS* | $8,917 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $1,895 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2136: Install / repair insulation on steam lines | $2,375 | $267 | - | - |
$2,375
-
MMBtu
|
- | - | |
| 02 | 3.1161: Eliminate/reduce an operation | $1,271 | $900 | - | - | - | - | $1,271 | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $194 | $208 |
$82
2,050
kWh
|
$23
-
kW-mo/yr
|
- | $89 | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,895 | $3,697 |
$1,042
26,051
kWh
|
$548
-
kW-mo/yr
|
- | $305 | - | |
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $3,182 | $15,784 | - | - |
$3,182
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $8,917 | $20,856 |
$1,124
28,101
kWh
|
$571
-
kW-mo/yr
|
$5,557
-
MMBtu
|
$394 | $1,271 | ||
| TOTAL IMPLEMENTED | $1,895 | $3,697 |
$1,042
26,051
kWh
|
$548
-
kW-mo/yr
|
- | $305 | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs