| Assessment Year | 2017 |
|---|---|
| Principal Product | Polystyrene Foam Products |
| NAICS | 326140: Polystyrene Foam Product Manufacturing |
| SIC | 3086: Plastics Foam Products |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
103,580
ft2
|
| Annual Production | 10,669,344
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $460,675 | 10,510,975 |
kWh
|
$0.044 | |
| Electricity Demand | $351,977 | 44,644 |
kW-mo/yr
|
$7.88 | |
| Electricity Fees | $21,527 | - |
|
- | |
| Natural Gas | $16,507 | 2,033 |
MMBtu
|
$8.12 | |
| Fuel Oil #1 | $5,911 | 568 |
MMBtu
|
$10.41 | |
| Waste Disposal Costs | |||||
| Water Usage | $768 | 124 |
Tgal
|
$6.19 | |
| TOTAL YEARLY COSTS | $857,365 | ||||
| RECOMMENDED SAVINGS* | $55,057 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $55,057 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8121: Apply for tax-free status for energy purchases | $18,874 | - | - | - | - | - | $18,874 | |
| 02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,132 | - |
$4,186
95,127
kWh
|
$946
-
kW-mo/yr
|
- | - | - | |
| 03 | 4.821: Pay bills on time to avoid late fees | $613 | - | - | - | - | - | $613 | |
| 04 | 2.8121: Apply for tax-free status for energy purchases | $579 | - | - | - | - | - | $579 | |
| 05 | 2.2437: Recover waste heat from equipment | $4,442 | $1,512 | - | - |
$4,442
-
MMBtu
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,066 | $3,806 |
$5,380
122,288
kWh
|
$1,608
-
kW-mo/yr
|
- | $770 | $1,308 | |
| 07 | 3.7312: Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings | $3,044 | $1,820 |
$3,044
69,184
kWh
|
- | - | - | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,147 | $975 |
$507
11,521
kWh
|
$249
-
kW-mo/yr
|
- | $14 | $377 | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $256 | $260 |
$108
2,460
kWh
|
$27
-
kW-mo/yr
|
- | $4 | $117 | |
| 10 | 2.7314: Reduce ventilation air | $680 | $913 |
$153
3,479
kWh
|
- |
$527
-
MMBtu
|
- | - | |
| 11 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $11,224 | $37,300 |
$9,018
204,958
kWh
|
$2,206
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $55,057 | $46,586 |
$22,396
509,017
kWh
|
$5,036
-
kW-mo/yr
|
$4,969
-
MMBtu
|
$788 | $21,868 | ||
| TOTAL IMPLEMENTED | $55,057 | $46,586 |
$22,396
509,017
kWh
|
$5,036
-
kW-mo/yr
|
$4,969
-
MMBtu
|
$788 | $21,868 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs