| Assessment Year | 2016 |
|---|---|
| Principal Product | Modular Oil Piping Packages |
| NAICS | 333999: All Other Miscellaneous General Purpose Machinery Manufacturing |
| SIC | 3561: Pumps and Pumping Equipment |
| Sales Range | $10 M to 50M |
| # of Employees | 110 |
| Plant Area |
90,000
ft2
|
| Annual Production | 115
units
|
| Production Hrs. Annual | 4,420
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $66,903 | 1,129,258 |
kWh
|
$0.059 |
| Electricity Demand | $28,354 | 3,359 |
kW-mo/yr
|
$8.44 |
| Natural Gas | $10,413 | 2,421 |
MMBtu
|
$4.30 |
| TOTAL YEARLY COSTS | $105,670 | |||
| RECOMMENDED SAVINGS* | $37,327 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $35,331 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,203 | - |
$1,493
25,308
kWh
|
- | - | $(-240.0) | $(-50.0) | |
| 02 | 4.821: Pay bills on time to avoid late fees | $229 | - | - | - | - | - | $229 | |
| 03 | 2.7224: Reduce space conditioning during non-working hours | $166 | - | - | - |
$166
-
MMBtu
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $602 | $412 |
$160
2,715
kWh
|
$31
-
kW-mo/yr
|
- | $292 | $119 | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $28,633 | $48,359 |
$23,157
392,496
kWh
|
$8,994
-
kW-mo/yr
|
- | $152 | $(-3,670.0) | |
| 06 | 2.7135: Install occupancy sensors | $702 | $1,456 |
$702
11,890
kWh
|
- | - | - | - | |
| 07 | 2.6211: Conserve energy by efficient use of vending machines | $155 | $360 |
$155
2,628
kWh
|
- | - | - | - | |
| 08 | 2.7314: Reduce ventilation air | $648 | $1,647 |
$131
2,172
kWh
|
- |
$517
-
MMBtu
|
- | - | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,529 | $4,023 |
$1,237
20,967
kWh
|
$486
-
kW-mo/yr
|
- | $16 | $(-210.0) | |
| 10 | 2.4322: Use or replace with energy efficient substitutes | $2,969 | $9,000 |
$690
11,700
kWh
|
$2,279
-
kW-mo/yr
|
- | - | - | |
| 11 | 2.4221: Install compressor air intakes in coolest locations | $491 | $1,610 |
$491
8,318
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $37,327 | $66,867 |
$28,216
478,194
kWh
|
$11,790
-
kW-mo/yr
|
$683
-
MMBtu
|
$220 | $(-3,582.0) | ||
| TOTAL IMPLEMENTED | $35,331 | $61,794 |
$26,737
453,186
kWh
|
$11,790
-
kW-mo/yr
|
$166
-
MMBtu
|
$220 | $(-3,582.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs