ITAC Assessment: SU0398
ITAC logo
ITAC Assessment: SU0398
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Electrical Insulated Sleeving
NAICS 335932: Noncurrent-Carrying Wiring Device Manufacturing
SIC 3644: Noncurrent-Carrying Wiring Devices
Sales Range $10
M
to 50
M
# of Employees 128
Plant Area 150,000
ft2
Annual Production 47,250
thousand feet
Production Hrs. Annual 5,880
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $169,552 2,909,923
kWh
Electricity Demand $67,519 6,782
kW-mo/yr
Electricity Fees $9,953 -
Natural Gas $63,832 10,727
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,699 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,086

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.4314: Use synthetic lubricant $7,708 - $5,706
98,373
kWh
$2,002
-
kW-mo/yr
- - -
02 2.7224: Reduce space conditioning during non-working hours $4,974 $127 - - $4,974
-
MMBtu
- -
03 2.7135: Install occupancy sensors $1,047 $332 $1,047
18,052
kWh
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $856 $555 $442
7,621
kWh
$87
-
kW-mo/yr
- $189 $138
05 2.6211: Conserve energy by efficient use of vending machines $680 $2,236 $680
11,716
kWh
- - - -
06 2.7314: Reduce ventilation air $311 $659 $155
2,673
kWh
- $156
-
MMBtu
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $2,378 $5,201 $1,606
27,695
kWh
$623
-
kW-mo/yr
- $71 $78
08 2.7135: Install occupancy sensors $51 $124 $51
882
kWh
- - - -
09 2.2442: Preheat combustion air with waste heat $5,694 $16,850 - - $5,694
-
MMBtu
- -
TOTAL RECOMMENDED $23,699 $26,084 $9,687
167,012
kWh
$2,712
-
kW-mo/yr
$10,824
-
MMBtu
$260 $216
TOTAL IMPLEMENTED $10,086 $5,201 $7,312
126,068
kWh
$2,625
-
kW-mo/yr
- $71 $78
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs