Assessment Year | 2015 |
---|---|
Principal Product | Mass transit and commuter buses |
NAICS | 336120: Heavy Duty Truck Manufacturing |
SIC | 3711: Motor Vehicles and Passenger Car Bodies |
Sales Range | $100 M to 500M |
# of Employees | 290 |
Plant Area |
147,500
ft2
|
Annual Production | 479
units
|
Production Hrs. Annual | 4,125
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $66,007 | 1,713,192 |
kWh
|
$0.039 |
Electricity Demand | $38,097 | 3,890 |
kW-mo/yr
|
$9.79 |
Electricity Fees | $61,217 | - |
|
- |
Natural Gas | $54,412 | 9,742 |
MMBtu
|
$5.59 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $41,223 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Consumption Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4322: Use or replace with energy efficient substitutes | $1,803 | - |
$702
18,000
kWh
|
$1,101
-
kW-mo/yr
|
- | - | - | |
02 | 2.8121: Apply for tax-free status for energy purchases | $1,211 | - | - | - | - | - | $1,211 | |
03 | 2.2511: Insulate bare equipment | $988 | $858 |
$(-59.0)
(-1,516)
kWh
|
$(-21.0)
-
kW-mo/yr
|
$1,068
-
MMBtu
|
- | - | |
04 | 3.4141: Replace the chlorination stage with an oxygen or ozone stage | $15,923 | $25,000 | - | - | - |
$15,923
-
Tgal
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $776 | $1,546 |
$263
6,745
kWh
|
$90
-
kW-mo/yr
|
- | - | $423 | |
06 | 3.1182: Make a new by-product | $20,522 | $100,000 |
$(-105.0)
(-2,683)
kWh
|
$(-2,448.0)
-
kW-mo/yr
|
- | - | $23,075 | |
TOTAL RECOMMENDED | $41,223 | $127,404 |
$801
20,546
kWh
|
$(-1,278.0)
-
kW-mo/yr
|
$1,068
-
MMBtu
|
$15,923
-
Tgal
|
$24,709 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Consumption Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs