Assessment Year | 2014 |
---|---|
Principal Product | Electrical Wiring Devices |
NAICS | 335931: Current-Carrying Wiring Device Manufacturing |
SIC | 3643: Current-Carrying Wiring Devices |
Sales Range | $10 M to 50M |
# of Employees | 96 |
Plant Area |
48,000
ft2
|
Annual Production | 120,000
pieces
|
Production Hrs. Annual | 2,340
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $10,002 | 312,640 |
kWh
|
$0.032 |
Electricity Demand | $2,817 | 704 |
kW-mo/yr
|
$4.00 |
Electricity Fees | $3,000 | - |
|
- |
Natural Gas | $4,743 | 793 |
MMBtu
|
$5.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,269 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,666 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4322: Use or replace with energy efficient substitutes | $2,635 | - |
$1,555
48,600
kWh
|
$1,080
-
kW-mo/yr
|
- | - | - | |
02 | 4.821: Pay bills on time to avoid late fees | $291 | - | - | - | - | - | $291 | |
03 | 2.7122: Disconnect ballasts | $148 | - |
$90
2,808
kWh
|
$58
-
kW-mo/yr
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,510 | $765 |
$106
3,328
kWh
|
$18
-
kW-mo/yr
|
- | $990 | $396 | |
05 | 2.4322: Use or replace with energy efficient substitutes | $580 | $1,126 | - | - |
$580
-
MMBtu
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $221 | $539 |
$135
4,212
kWh
|
$86
-
kW-mo/yr
|
- | - | - | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $496 | $2,007 |
$496
15,505
kWh
|
- | - | - | - | |
08 | 3.1161: Eliminate/reduce an operation | $388 | $1,660 |
$(-13.0)
(-420)
kWh
|
$(-144.0)
-
kW-mo/yr
|
- | $210 | $335 | |
TOTAL RECOMMENDED | $6,269 | $6,097 |
$2,369
74,033
kWh
|
$1,098
-
kW-mo/yr
|
$580
-
MMBtu
|
$1,200 | $1,022 | ||
TOTAL IMPLEMENTED | $2,666 | $3,311 |
$827
25,853
kWh
|
$162
-
kW-mo/yr
|
- | $990 | $687 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs