| Assessment Year | 2014 |
|---|---|
| Principal Product | Components and subassemblies for medical and defense applications |
| NAICS | 332710: Machine Shops |
| SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 55 |
| Plant Area |
32,000
ft2
|
| Annual Production | 61,783
pieces
|
| Production Hrs. Annual | 6,500
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $43,735 | 1,077,653 |
kWh
|
$0.041 |
| Electricity Demand | $42,686 | 2,732 |
kW-mo/yr
|
$15.62 |
| Electricity Fees | $9,872 | - |
|
- |
| Natural Gas | $5,957 | 669 |
MMBtu
|
$8.90 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $15,640 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,541 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4322: Use or replace with energy efficient substitutes | $1,104 | - |
$354
8,640
kWh
|
$750
-
kW-mo/yr
|
- | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,078 | $20,000 |
$1,078
26,300
kWh
|
- | - | - | |
| 03 | 2.7224: Reduce space conditioning during non-working hours | $463 | - | - | - |
$463
-
MMBtu
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,903 | $1,500 |
$2,903
70,800
kWh
|
- | - | - | |
| 05 | 2.7134: Use photocell controls | $765 | $1,578 |
$765
18,668
kWh
|
- | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,180 | $15,512 |
$3,998
97,500
kWh
|
$2,813
-
kW-mo/yr
|
- | $369 | |
| 07 | 2.7135: Install occupancy sensors | $1,532 | $3,780 |
$1,532
37,375
kWh
|
- | - | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $615 | $3,090 |
$269
6,570
kWh
|
$281
-
kW-mo/yr
|
- | $65 | |
| TOTAL RECOMMENDED | $15,640 | $45,460 |
$10,899
265,853
kWh
|
$3,844
-
kW-mo/yr
|
$463
-
MMBtu
|
$434 | ||
| TOTAL IMPLEMENTED | $1,541 | $20,000 |
$1,078
26,300
kWh
|
- |
$463
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs