| Assessment Year | 2014 |
|---|---|
| Principal Product | Electrical Fittings |
| NAICS | 335932: Noncurrent-Carrying Wiring Device Manufacturing |
| SIC | 3644: Noncurrent-Carrying Wiring Devices |
| Sales Range | $50 M to 100M |
| # of Employees | 118 |
| Plant Area |
139,887
ft2
|
| Annual Production | 1,520,000
units
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $534,736 | 9,040,073 |
kWh
|
$0.059 |
| Electricity Demand | $99,266 | 35,828 |
kW-mo/yr
|
$2.77 |
| Electricity Fees | $4,677 | - |
|
- |
| Natural Gas | $398,038 | 67,082 |
MMBtu
|
$5.93 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,585 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,452 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2136: Install / repair insulation on steam lines | $1,295 | $202 | - | - |
$1,295
-
MMBtu
|
- | - | |
| 02 | 2.7135: Install occupancy sensors | $2,464 | $1,840 |
$2,464
41,760
kWh
|
- | - | - | - | |
| 03 | 2.6211: Conserve energy by efficient use of vending machines | $1,404 | $2,959 |
$1,404
23,795
kWh
|
- | - | - | - | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $8,593 | $15,784 | - | - |
$8,593
-
MMBtu
|
- | - | |
| 05 | 3.1161: Eliminate/reduce an operation | $4,540 | $15,840 |
$(-133.0)
(-2,256)
kWh
|
$(-1,097.0)
-
kW-mo/yr
|
- | $1,080 | $4,690 | |
| 06 | 2.4321: Upgrade obsolete equipment | $289 | $1,250 |
$268
4,536
kWh
|
$21
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $18,585 | $37,875 |
$4,003
67,835
kWh
|
$(-1,076.0)
-
kW-mo/yr
|
$9,888
-
MMBtu
|
$1,080 | $4,690 | ||
| TOTAL IMPLEMENTED | $5,452 | $6,251 |
$4,136
70,091
kWh
|
$21
-
kW-mo/yr
|
$1,295
-
MMBtu
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs