ITAC Assessment: SU0353
ITAC logo
ITAC Assessment: SU0353
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Acrylic and Oil Pants for Fine Artists
NAICS 325510: Paint and Coating Manufacturing
SIC 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products
Sales Range $10
M
to 50
M
# of Employees 159
Plant Area 149,000
ft2
Annual Production 820,000
units
Production Hrs. Annual 4,316
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $72,387 976,880
kWh
Electricity Demand $22,926 2,770
kW-mo/yr
Electricity Fees $5,935 -
Fuel Oil #2 $51,940 1,960
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $45,924 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $39,880

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $839 - $640
8,632
kWh
$199
-
kW-mo/yr
- - -
02 2.2437: Recover waste heat from equipment $6,044 $1,188 - - $6,044
-
MMBtu
- -
03 2.7135: Install occupancy sensors $896 $273 $896
12,086
kWh
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $424 $345 $102
1,381
kWh
$31
-
kW-mo/yr
- - $291
05 2.1332: Convert combustion equipment to burn natural gas $2,685 $3,075 - - - - $2,685
06 2.1224: Replace boiler $34,391 $40,935 - - - $4,440 $29,951
07 2.4221: Install compressor air intakes in coolest locations $627 $737 $627
8,462
kWh
- - - -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $18 $29 $18
241
kWh
- - - -
TOTAL RECOMMENDED $45,924 $46,582 $2,283
30,802
kWh
$230
-
kW-mo/yr
$6,044
-
MMBtu
$4,440 $32,927
TOTAL IMPLEMENTED $39,880 $45,394 $2,283
30,802
kWh
$230
-
kW-mo/yr
- $4,440 $32,927
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs