Assessment Year | 2013 |
---|---|
Principal Product | Medical Diagnostics Products |
NAICS | 334510: Electromedical and Electrotherapeutic Apparatus Manufacturing |
SIC | 3845: Electromedical and Electrotherapeutic Apparatus |
Sales Range | $100 M to 500M |
# of Employees | 910 |
Plant Area |
300,000
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $529,827 | 11,297,580 |
kWh
|
$0.047 |
Electricity Demand | $301,845 | 25,379 |
kW-mo/yr
|
$11.89 |
Electricity Fees | $12,689 | - |
|
- |
Natural Gas | $217,199 | 34,972 |
MMBtu
|
$6.21 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $71,432 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $52,510 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7224: Reduce space conditioning during non-working hours | $10,408 | - | - | - |
$10,408
-
MMBtu
|
- | |
02 | 3.5316: Contract a wood pallet recycling company | $8,049 | - | - | - | - | $8,049 | |
03 | 4.821: Pay bills on time to avoid late fees | $1,239 | - | - | - | - | $1,239 | |
04 | 2.7132: Install timers on light switches in little used areas | $30,158 | $131 |
$30,158
641,555
kWh
|
- | - | - | |
05 | 2.7111: Reduce illumination to minimum necessary levels | $741 | $191 |
$313
6,656
kWh
|
$428
-
kW-mo/yr
|
- | - | |
06 | 2.2123: Insulate feedwater tank | $579 | $190 | - | - |
$579
-
MMBtu
|
- | |
07 | 2.2136: Install / repair insulation on steam lines | $579 | $340 | - | - |
$579
-
MMBtu
|
- | |
08 | 3.1161: Eliminate/reduce an operation | $18,624 | $29,949 |
$(-88.0)
(-1,875)
kWh
|
$(-642.0)
-
kW-mo/yr
|
- | $19,354 | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $347 | $771 |
$290
6,176
kWh
|
$57
-
kW-mo/yr
|
- | - | |
10 | 2.7243: Improve air circulation with destratification fans / other methods | $298 | $705 |
$(-53.0)
(-1,121)
kWh
|
$(-3.0)
-
kW-mo/yr
|
$354
-
MMBtu
|
- | |
11 | 2.6211: Conserve energy by efficient use of vending machines | $221 | $616 |
$221
4,693
kWh
|
- | - | - | |
12 | 2.4321: Upgrade obsolete equipment | $189 | $852 |
$130
2,756
kWh
|
$59
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $71,432 | $33,745 |
$30,971
658,840
kWh
|
$(-101.0)
-
kW-mo/yr
|
$11,920
-
MMBtu
|
$28,642 | ||
TOTAL IMPLEMENTED | $52,510 | $3,091 |
$31,112
661,836
kWh
|
$544
-
kW-mo/yr
|
$11,566
-
MMBtu
|
$9,288 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs