ITAC Assessment: SD0404
ITAC logo
ITAC Assessment: SD0404
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Metal Filing Cabinets
NAICS 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 140
Plant Area 110,000
ft2
Annual Production 20,000,000
units
Production Hrs. Annual 2,250
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $125,155 1,312,616
kWh
Electricity Demand $65,469 3,588
kW-mo/yr
Natural Gas $126,010 15,388
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $112,240 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $32,090

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $4,578 - $4,578
7,091
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $18,544 $29,161 $12,542
131,539
kWh
$6,002
-
kW-mo/yr
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $14,356 $8,130 $9,282
97,397
kWh
$5,074
-
kW-mo/yr
-
04 2.2414: Use waste heat from hot flue gases to preheat $1,382 $4,270 - - $1,382
-
MMBtu
05 2.2449: Recover heat from exhausted steam, hot air or hot water $1,071 $2,035 - - $1,071
-
MMBtu
06 2.4133: Use most efficient type of electric motors $2,452 $2,144 $1,649
17,296
kWh
$803
-
kW-mo/yr
-
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,750 $5,772 $1,750
18,359
kWh
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $1,928 $3,189 $1,304
13,680
kWh
$624
-
kW-mo/yr
-
09 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $62,662 $213,472 $30,435
319,200
kWh
$17,520
-
kW-mo/yr
$14,707
-
MMBtu
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,517 $720 $2,276
23,880
kWh
$1,241
-
kW-mo/yr
-
TOTAL RECOMMENDED $112,240 $268,893 $63,816
628,442
kWh
$31,264
-
kW-mo/yr
$17,160
-
MMBtu
TOTAL IMPLEMENTED $32,090 $37,249 $22,349
193,486
kWh
$8,670
-
kW-mo/yr
$1,071
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs