ITAC Assessment: SU0338
ITAC logo
ITAC Assessment: SU0338
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Oral solid dose pharmaceuticals
NAICS 325412: Pharmaceutical Preparation Manufacturing
SIC 2834: Pharmaceutical Preparations
Sales Range $50
M
to 100
M
# of Employees 414
Plant Area 384,000
ft2
Annual Production 755,000,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) New York

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $852,904 13,822,252
kWh
Electricity Demand $94,722 24,343
kW-mo/yr
Electricity Fees $8,522 -
Natural Gas $311,556 52,292
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $256,101 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $42,923

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 4.821: Pay bills on time to avoid late fees $3,233 - - - - - $3,233
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $111,890 $4,878 $112,147
1,817,622
kWh
$(-257.0)
-
kW-mo/yr
- - -
03 4.426: Modify workload $80,009 $2,213 - - - $80,009 -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $39,567 $2,727 $39,567
641,288
kWh
- - - -
05 3.1161: Eliminate/reduce an operation $11,039 $5,760 $(-107.0)
(-1,733)
kWh
$(-280.0)
-
kW-mo/yr
- $1,252 $10,174
06 2.2136: Install / repair insulation on steam lines $513 $294 - - $513
-
MMBtu
- -
07 2.7444: Close holes and openings in building such as broken windows $59 $46 - - $59
-
MMBtu
- -
08 2.7314: Reduce ventilation air $3,034 $5,294 $227
3,682
kWh
$28
-
kW-mo/yr
$2,779
-
MMBtu
- -
09 2.2414: Use waste heat from hot flue gases to preheat $6,693 $15,784 - - $6,693
-
MMBtu
- -
10 2.4321: Upgrade obsolete equipment $64 $224 $59
964
kWh
$5
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $256,101 $37,220 $151,893
2,461,823
kWh
$(-504.0)
-
kW-mo/yr
$10,044
-
MMBtu
$81,261 $13,407
TOTAL IMPLEMENTED $42,923 $2,997 $39,626
642,252
kWh
$5
-
kW-mo/yr
$59
-
MMBtu
- $3,233
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs