Assessment Year | 2013 |
---|---|
Principal Product | Asphalt |
NAICS | 324121: Asphalt Paving Mixture and Block Manufacturing |
SIC | 2951: Asphalt Paving Mixtures and Blocks |
Sales Range | $1 M to 5M |
# of Employees | 6 |
Plant Area |
12,800
ft2
|
Annual Production | 63,286
ton
|
Production Hrs. Annual | 2,120
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $45,168 | 157,248 |
kWh
|
$0.29 |
Fuel Oil #2 | $422,878 | 15,092 |
MMBtu
|
$28.02 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $312,429 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $291,300 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $20,297 | $5,686 |
$20,297
69,957
kWh
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $832 | $386 |
$832
2,869
kWh
|
- | |
03 | 2.1331: Burn a less expensive grade of fuel | $288,725 | $218,600 | - | $288,725 | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,709 | $5,124 |
$1,709
5,894
kWh
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $866 | $2,820 |
$866
2,985
kWh
|
- | |
TOTAL RECOMMENDED | $312,429 | $232,616 |
$23,704
81,705
kWh
|
$288,725 | ||
TOTAL IMPLEMENTED | $291,300 | $226,544 |
$2,575
8,879
kWh
|
$288,725 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs