| Assessment Year | 2009 |
|---|---|
| Principal Product | Rolled Aluminum |
| NAICS | 331315: Aluminum Sheet, Plate, and Foil Manufacturing |
| SIC | 3353: Aluminum Sheet, Plate, and Foil |
| Sales Range | greater than $500 M |
| # of Employees | 675 |
| Plant Area |
1,611,720
ft2
|
| Annual Production | 1,300,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | New York |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $21,308,952 | 261,939,779 |
kWh
|
$0.081 |
| Electricity Fees | $216,000 | - |
|
- |
| Natural Gas | $34,714,592 | 3,014,433 |
MMBtu
|
$11.52 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $424,655 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $398,662 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $97,827 | - |
$97,827
1,207,741
kWh
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,818 | $800 |
$5,818
71,832
kWh
|
- | |
| 03 | 2.2511: Insulate bare equipment | $2,108 | $155 | - |
$2,108
-
MMBtu
|
|
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $23,109 | $11,160 | - |
$23,109
-
MMBtu
|
|
| 05 | 2.7135: Install occupancy sensors | $2,884 | $833 |
$2,884
35,609
kWh
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $292,552 | $333,015 |
$292,552
3,611,748
kWh
|
- | |
| 07 | 2.6211: Conserve energy by efficient use of vending machines | $357 | $1,608 |
$357
4,402
kWh
|
- | |
| TOTAL RECOMMENDED | $424,655 | $347,571 |
$399,438
4,931,332
kWh
|
$25,217
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $398,662 | $335,578 |
$396,554
4,895,723
kWh
|
$2,108
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs