Assessment Year | 2006 |
---|---|
Principal Product | Fluid Milk Products |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2026: Fluid Milk |
Sales Range | $10 M to 50M |
# of Employees | 62 |
Plant Area |
78,000
ft2
|
Annual Production | 17,000
Tgal
|
Production Hrs. Annual | 7,512
hrs
|
Location (State) | New York |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $473,466 | 5,754,000 |
kWh
|
$0.082 |
Electricity Demand | $34,615 | 11,568 |
kW-mo/yr
|
$2.99 |
Electricity Fees | $5,565 | - |
|
- |
Natural Gas | $410,250 | 34,526 |
MMBtu
|
$11.88 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $84,966 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $48,559 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,479 | - |
$3,251
39,638
kWh
|
$228
-
kW-mo/yr
|
- | |
02 | 2.2135: Repair and eliminate steam leaks | $41,200 | $140 | - | - |
$41,200
-
MMBtu
|
|
03 | 2.2136: Install / repair insulation on steam lines | $3,956 | $742 | - | - |
$3,956
-
MMBtu
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,403 | $572 |
$3,215
39,213
kWh
|
$188
-
kW-mo/yr
|
- | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $32,813 | $10,389 | - | - |
$32,813
-
MMBtu
|
|
06 | 2.6211: Conserve energy by efficient use of vending machines | $115 | $271 |
$115
1,397
kWh
|
- | - | |
TOTAL RECOMMENDED | $84,966 | $12,114 |
$6,581
80,248
kWh
|
$416
-
kW-mo/yr
|
$77,969
-
MMBtu
|
||
TOTAL IMPLEMENTED | $48,559 | $1,454 |
$3,215
39,213
kWh
|
$188
-
kW-mo/yr
|
$45,156
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs